Yes. Our own vehicle and equipment fleet, heavy transport logistics and trained teams enable work outside Austria. Project-specific safety and site access instructions are taken into account.
Steel construction: site inspection and measurement → engineering calculations and 3D planning → fabrication and inspection → delivery and installation.
Cable projects: coordinate route, cable and drum → select pulling and transport equipment → cable pulling and installation → testing and documented handover.
Both companies work together so site requirements inform planning and fabrication from the outset.
Clients and partners include ELIN, VERBUND, EQOS Energie, Südkabel, ÖBB, EVN, Energie Steiermark and Wiener Netze.
The group comprises three companies headquartered in Wildon, Styria: Powoden Holding GmbH (group holding company), Powoden Energie- & Bautechnik GmbH (cable pulling and installation for industry and energy), and Powoden Power Technologies GmbH (design and fabrication of steel structures). Fabrication and on-site execution work together within one group.
Monday–Thursday 07:00–16:00, Friday 07:00–12:00. Closed Saturday and Sunday. You can send urgent enquiries via WhatsApp (+43 664 923 14 59) or email (office@powoden.com) at any time.
Powoden Power Technologies GmbH fabricates steel and welded structures and cable drums; the website shows galvanised components. Please contact us to discuss the surface treatment for your project: +43 664 923 14 59 or office@powoden.com.
Production in Söding uses TIG, MAG and manual metal arc welding, as well as CNC machining. Welding processes are monitored and inspections documented. Powoden Power Technologies GmbH has IWS/IWT welding coordination and Level 2 VT/PT/MT inspection personnel. Fabrication is certified to EN 1090 (up to EXC3) and EN ISO 3834-2.
Yes. Powoden Energie- & Bautechnik GmbH uses sheath testing equipment to test cable systems and document the results. Employees receive instruction in operating and maintaining this equipment.
Yes. Powoden Energie- & Bautechnik GmbH handles installation, drum logistics, cable crossings, testing and dismantling of temporary cable connections, planned and documented to project requirements.
Powoden Holding GmbH: VAT ATU82939705, registration FN 621490g, Regional Court for Civil Matters Graz.
Powoden Energie- & Bautechnik GmbH: VAT ATU68129303, registration FN 399319i, Regional Court for Civil Matters Graz.
Powoden Power Technologies GmbH: VAT ATU82966907, registration FN 669214p.
Registered office of all three companies: Leibnitzer Straße 9, A-8410 Wildon.
Yes. Powoden Energie- & Bautechnik GmbH provides cable pulling and installation as well as electrical and steel installation (cable trays, supports and brackets). For major projects, Powoden works with an independent partner in KABEL ARGE GnbR, which carries out joints, terminations and testing.
Powoden Energie- & Bautechnik GmbH performs heavy cable pulling for high- and extra-high-voltage cables with conductor cross-sections up to 2,500 mm², at 110 kV, 220 kV and 380 kV. Pulling equipment, drum logistics and machinery are selected for each project according to drum weight, cable, route and site conditions.
Equipment is selected and availability agreed for each project.
Transport and cranes: Mercedes-Benz Arocs 4152 8×6, Tatra Phönix 530 8×8, Scania and MAN vehicles.
Cable transport and payout: Bagela, Thaler and Vetter cable trailers, drum stands and payout equipment up to 110 tonnes.
Site vehicles: Unimog U530, MAN TGE 4×4 and installation vehicles.
Pulling and pushing: Volta tracked winch, Zeck and Volta capstan winches, Lancier cable caterpillars and pushing equipment.
Installation and testing: mobile jointing containers, hydraulic units, rollers and crossbeams, pulling force monitoring and sheath testing equipment.
Employees receive task-specific training and regular instruction: SCC safety qualification, electrically instructed persons (ETuP), confined spaces, working at height and fall protection, first aid including AED, escape hoods, slinging loads, forklift qualifications, cable pulling equipment, sheath testing and cable stripping equipment. Site-specific safety instruction and emergency and evacuation exercises are included. Production also has IWS/IWT welding coordination and Level 2 VT/PT/MT inspection personnel.
For project enquiries and quotations, contact +43 664 923 14 59 or office@powoden.com. Team contacts include Armin Grasel (sales), Dieter Schnalzer (project management), Jürgen Matzer (office management), Detlev Platzer (technology and fleet), and Reimund Pich (site management). Please copy office@powoden.com when emailing individual team members.
Design and fabrication in Söding: steel structures for conveyor systems; structures and components for energy installations; cable supports, brackets and crossings; heavy steel and bespoke welded structures; steel cable drums; series and precision production and CNC machining. Services cover inspection, measurement, 3D planning, fabrication, delivery and installation.
Powoden Energie- & Bautechnik GmbH: ISO 9001:2015 (Q7-33889/0, valid until 4 October 2027), ISO 14001:2015 (U7-05527/0, valid until 27 October 2028), ISO 45001:2018 (OHS7-02117/0, valid until 4 October 2027).
Powoden Power Technologies GmbH: ISO 9001, ISO 14001, ISO 45001, EN 1090-1 (up to EXC3), EN ISO 3834-2 and ÖN EN ISO 17660-1. Certificates are available on the Downloads page.
Powoden and a long-standing independent partner form KABEL ARGE GnbR to deliver major energy infrastructure projects together. The partner handles cable installation, joints, terminations, high-voltage testing and commissioning. Powoden handles cable pulling, steel construction, civil works, logistics and project delivery. The partner is an independent company outside the Powoden Group.
Yes. Powoden Power Technologies GmbH fabricates project-specific steel and welded structures, from site inspection and measurement through engineering calculations and 3D planning to fabrication, delivery and coordinated installation. Send drawings, requirements or your project idea to office@powoden.com or call +43 664 923 14 59.
Cable pulling and installation for industry, high and extra-high voltage; temporary construction power cables including drum logistics, crossings, testing and dismantling; electrical and steel installation including cable trays, supports and brackets; trenches, foundations, cable ducts and conduit systems; dismantling of cables and plant components; drum transport and installation equipment.
The group has almost 100 employees: around 50 at Powoden Energie- & Bautechnik GmbH and around 25 at Powoden Power Technologies GmbH. Powoden Holding GmbH provides strategic management and group administration.
Powoden Power Technologies GmbH was formed on 1 April 2026 through the acquisition of the metalworking and steel construction division of Gänsweider Metalltechnik GmbH, a business with more than 100 years of experience. Employees, machinery, expertise and customer relationships were taken over. The present company has existed since 2026.
Registered office of all companies: Leibnitzer Straße 9, A-8410 Wildon.
Powoden Energie- & Bautechnik GmbH office and warehouse: Greith 4, A-8410 Lichendorf.
Powoden Power Technologies GmbH production: Packer Straße 175, A-8561 Söding (visits by appointment).
Central contact: telephone / WhatsApp +43 664 923 14 59, office@powoden.com.
Direct contact for Powoden Energie- & Bautechnik GmbH: +43 664 306 27 95, office@powodenenergie.at.
Opening hours: Monday–Thursday 07:00–16:00, Friday 07:00–12:00.
Peter Powoden is managing director of Powoden Holding GmbH. At Powoden Energie- & Bautechnik GmbH, Corina Powoden also serves as managing director, with further contacts for sales, project management, technology and site management. Team responsibilities differ; Jürgen Matzer is responsible for office management at Powoden Energie- & Bautechnik GmbH.
Have another question? Contact our team.